Doolee scope includes bulk earthworks, road construction, sealing, cell lining, pipework along with weighbridge, site offices and other associated facilities. With strict city and state regulations around the control of dust onsite, Doolee were needing a new standpipe as part of a wider truck fill dust suppression strategy.
Being a remote project, located just outside Gin Gin, Doolee needed a standpipe package they could move around quickly and safely, and relocate to the next site when finished.
With poor water quality, Doolee also required a water management package and standpipe that would be corrosion resistant – steel would not have been suitable for this site.
Francis Lee, Doolee’s Construction Director contacted Liquimech to source a solution.
Liquimech was able to deliver a full dust suppression package including HDPE standpipe, pipe floats and pump.
The ease of installation and relocation of the Liquimech’s patented standpipe addressed the need for movement throughout the site and to further sites.
Because of the corrosion-resistant properties of the HDPE, the Liquimech Standpipe was able to handle the rough water quality and tough conditions of the remote site.
Liquimech reached out to Francis to see how the project is going.
How did you find the Liquimech customer experience?
Response to customer requirements?
Thank you Doolee Constructions.